Leeward Construction Co. v. American Univ. of Antigua

by
This case arose when Leeward and AUA entered into an agreement for Leeward to build a medical school for AUA in Antigua. AUA subsequently appealed the district court's confirmation of an international arbitration award entered in favor of Leeward. AUA principally argues that the district court erred in confirming the award because the arbitration panel failed to fulfill its obligation to produce a reasoned award.The court held, however, that an arbitration decision need not contain a line‐by‐line analysis of damages awarded to be considered a reasoned award. Rather, an arbitration award is a reasoned award when it contains a substantive discussion of the panel’s rationale. The court considered AUA's remaining arguments and found them to be without merit. Accordingly, the court affirmed the judgment. The court disposed of Case No. 15-1595-cv in a separate summary order issued concurrently with this decision. View "Leeward Construction Co. v. American Univ. of Antigua" on Justia Law